Answer:
the overhead cost assigned is $7,930.02
Step-by-step explanation:
The computation of the overhead cost assigned to Product Q79P is shown below:
= (Number of assembly hours × Activity rate per assembly hour) + (Number of customer orders × Activity rate per customer order) + (Number of batches × Activity rate per batch)
= (252 × $2.86) + (42 × $48.23) + (68 × $76.23)
= $720.72 + $2,025.66 + $5,183.64
= $7,930.02
hence, the overhead cost assigned is $7,930.02