Assume that you have crashed a project as much as possible, but the length of the critical path is still not acceptable. What other options are available

User Bughi
by
7.9k points

1 Answer

3 votes

Answer:

Critical chain project management

Step-by-step explanation:

While Critical path typically consider the duration of the project by the task measures from the personnel involved

Critical chain project management on the other hand considers projects from the viewpoint of resources. This helps to put much focus on the end goal instead of each task duration, thereby making sure there is the availability of resources for each critical task.