Answer:
What is the initial cost of the project?
the initial cost or initial outlay = $100
how much value is created?
the NPV of the project = -$100 + $50/1.1 + $50/1.1² + $50/1.1³ = $24.34
the NPV basically gives us how much value or wealth is created by the project
and what would you be willing to sell the project for?
selling price = $124.34 (= initial outlay + NPV)