Answer:
Total budgeted overhead= $224,800
Step-by-step explanation:
Giving the following information:
Each unit requires 4 hours of direct labor at a rate of $16 per hour.
Suppose 1,000 units are budgeted to produce.
First, we need to calculate the direct labor cost:
Direct labor cost= (4*16)*1,000= $64,000
Now, the overhead budget:
Variable overhed= 64,000*0.7= $44,800
Fixed overhead= 180,000
Total budgeted overhead= $224,800