19.0k views
1 vote
AAA has a contract to build a building for $ 100,000 with an estimated time to completion of three years. A reliable cost estimate for the project is $ 60,000. In the first year of the project, AAA incurred costs totaling $ 24,000. How much profi t should AAA report at the end of the fi rst year under the percentage-of-completion method?

User Coretta
by
7.9k points

1 Answer

2 votes

Answer:

the profit that should be recorded is $16,000

Step-by-step explanation:

The computation of the profit that should be reported is shown below:

= (Incurred cost ÷ Estimation of the cost × Contract price) - (Incurred cost)

= ($24,000 ÷ $60,000 × $100,000) - ($24,000)

= $40,000 - $24,000

= $16,000

Hence, the profit that should be recorded is $16,000

We simply applied the above formula so that the correct value could come

And, the same is to be considered

User Gonzo
by
8.7k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.