Answer:
12.34%
Step-by-step explanation:
initial outlay = -$1,875,000
NCF year 1 = $415,350
NCF year 2 = $415,350
NCF year 3 = $415,350
NCF year 4 = $415,350
NCF year 5 = $415,350
NCF year 6 = $415,350
NCF year 7 = $415,350
using a financial calculator or an excel spreadsheet, IRR = 12.3.4%
the internal rate of return is the discount rate at which a project's NPV = 0