171k views
0 votes
Abnormal spoilage was 100 units and normal spoilage is 400 units. Beginning Work-in-Process Inventory consisted of 5,000 units; 20,000 units were started; and 22,000 units were completed this period. How many units were in ending Work-in-Process

User Mansur
by
4.2k points

1 Answer

4 votes

Answer: 2500

Step-by-step explanation:

The ending work in progress will be calculated as the addition of the begining work in progress to the units started for the year after which we then deduct the normal spoilage, abnormal spoilage and the units completed from the period. This will be:

= 5000 + 20000 - 22000 - 400 - 100

= 2500

The ending work in progress will be 2500.

User Vemka
by
5.4k points