Answer:
Factory overhead for the May month $7,480
Step-by-step explanation:
The computation of the factory overhead incurred is shown below:
Indirect labor $5,600
Property taxes on production equipment $880
Heat light and power $900
Insurance on plant and equipment $100
Factory overhead for the May month $7,480
We simply applied the above cost as they are not related to the production