5 men are hired to complete a job. If one more man is hired, the job can be completed 8 days earlier.

Assuming that all men work at the same rate how many more men should be hired so that the job can be completed 28 days earlier.

User Webmaster
by
5.6k points

1 Answer

4 votes

Answer:

The answer is 4 more men should be hired because when you added one more person you got 8 days earlier that the job was done... So, 8 times 4 is 32 which is bigger than 28 so that's how I got 4 more men... Hope this helps... Stay safe and have a great weekend... :D