18.3k views
11 votes
10 workers take 5 days at 3 hours per day to repair abroad. How many days for two road workers at 5 hours each day?

User Adnan Boz
by
7.0k points

1 Answer

8 votes

Answer:


\huge\underline\color{skyblue}{Answer ☘}


10 \: people * 3 \: hrs/day = \\ 30 \: man \: hrs/ \: day \\ \\ 2 \: people * 5 \: hrs/day = \\ 10 \: man \: hrs \: per/day \\ \\ 2 \: people \: work \: 5 \: hrs \: a \: day, \: so \: they \: \\deliver \: 10 \: man \: hours \: a \: day. \\ To \: finish \: a \: work \: of \: 100 \: man \: hours , \\ they’ll \: need \\ \\ (100)/(10) = 10 \: days

hope helpful~

User Chengcj
by
7.7k points