Answer:
81.25%
Step-by-step explanation:
the learning percentage = 26 hours / 32 hours = 0.8125 = 81.25%
The learning percentage is useful in order to calculate the cumulative average time and cost. Based on the information above and using a cumulative improvement factor table, we can estimate the number of hours required to manufacture a larger number of units.