Gray used a pulley to lift a 300 N object a distance of 3 m. It took Gray 30 seconds to lift the object. How much WORK did Gray exert?

1 Answer

7 votes

Answer:

900J

Step-by-step explanation:

The Work done can be calculated using

Work done = force × distance

According to this question, force = 300N, distance = 3m

Work done = 300 × 3

Work done = 900J

Gray exerted 900J of work