Assume you are managing an assembly line with 7 stations/workers and you know the following: 7 people working ... 20 pieces per hour, 71% efficiency 5 people working ... 15 pieces per hour, 75% efficiency 4 people working ... 13 pieces per hour, 87% efficiency Your boss calls to tell you that operating costs per product are too high. What do you do

User Looper
by
4.2k points

1 Answer

1 vote

Answer:

Utilize 4 people on the line

Step-by-step explanation:

Here you want to utilize the four people who are on the line as the efficiency could be increased by having minimum 10-15 points also at the same time the number of workers would be decreased by a significant margin

Therefore the option fourth is correct

And, the same is to be considered

All other options are wrong