Answer:
0.0401
Step-by-step explanation:
Calculation for the probability that the cost will exceed the budgeted amount
Based on the information given Mean = μ = $5,500 and Standard deviation =σ = $400
P(x > 6,200) = 1 - P(x <6,200 )
= 1 - P((x - μ ) / σ < ( 6,200 - 5,500) / 400)
= 1 - P(z < 1.75 )
= 1 - 0.9599 using the standard normal table,
= 0.0401
P(x > 6,200 ) = 0.0401
Hence,
Probability = 0.0401
Therefore the probability that the cost will exceed the budgeted amount will be 0.0401