Select the correct answer.
Feather Light Footwear approaches Roy and his team to develop a website that will help increase the company's sales and customer base. Apart
from other items that are clarified in the requirements-gathering session, the client insists on a speedy launch of the site, in two months flat. Roy
and his team already have partially complete projects for other clients that they must complete first. How should Roy handle this situation?
OA. Roy can put aside his current projects and prioritize to finish this new project before the others.
OB. Roy should commit to the project deadline and then later change the delivery date as they work on the project.
OC. Roy can commit to the timeline set by the client and make his team work overtime each day to meet the deadline.
OD. Roy can take up the project, hire additional resources, and later charge the client additional fees for the extra hires.
OE. Roy should be honest and agree on a reasonable timeline that he and his team can easily meet.