Answer:
The Direct Labor Utilization is:
71.8%
Step-by-step explanation:
Data and Calculations:
Total Direct labor Content = 280
Process Cycle Time = 65
Number of Workers = 6
Available labor time = Process Cycle Time * Number of Workers
= 65 * 6 = 390
The Direct Labor Utilization = Direct labor content/Available labor time * 100
= 280/390 * 100
= 71.8%
The direct labor utilization rate shows the usage of direct labor for actual production as opposed to idle time.