Answer:
D) 90 Days
Explanation:
dredge 1 min = 3 people days
when I say people days, I mean 3 people working one day
multiply each side by 60 to get the desired 60 min of dredge:
dredge 60 min = 180 people days
As we currently have this set up, it will take 180 people, 1 day to do the same amount of work as 60 min of dredge, but we only want 2 people. This means we need to divide the people days by 2 to get how many days are needed for 2 people, thus:
dredge 60 min = 2 people for 90 days