Holiday Laboratories purchased a high-speed industrial centrifuge at a cost of $470,000. Shipping costs totaled $14,100. Foundation work to house the centrifuge cost $7,700. An additional water line had to be run to the equipment at a cost of $2,600. Labor and testing costs totaled $7,000. Materials used up in testing cost $3,700. (Leave no cells blank. Enter 0 where needed.) a. What is the total cost of the equipment

User Br Araujo
by
4.6k points

1 Answer

3 votes

Answer:Total Cost of equipment=$502,500

Step-by-step explanation:

Total Cost of equipment= This is gotten by addition of Cost of Purchase +Shipping costs +Foundation work+ Testing expense

=$470,000+$14,100+$7,700+($7,000+$3,700.)

=$502,500