What does the measurement tell you?

Estimate at completion

2 Answers

3 votes
Measurement tells u the accurate measure of something
User Diamondsea
by
5.0k points
1 vote

Answer:

forecasted cost of the project, as the project progresses/"The expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete." - PMBOK Guide

Step-by-step explanation: