Answer:
5000 units.
Step-by-step explanation:
Kindly check the attachment for the diagram.
In order to solve this question that is the Determination of the minimum batch size that would enable the stenciling operation to meet daily demand, what we have to do is to divide the total number of time operation done per day by the Takt time.
The takt time = 7.5 hours a day × 3600/ 5000 daily demand rate.
The Takt time = 5.4 seconds.
Hence, the minimum batch size that would enable the stenciling operation to meet daily demand = 5000 from the given diagram