Answer:
the contractor should build 210 Carolina type homes and 60 Savannah type homes
Step-by-step explanation:
you have to maximize the following equation: 80000C + 90000S
Where:
C = Carolina type homes
S = Savannah type homes
the constraints are:
160000C + 240000S ≤ 48000000
160C + 160S ≤ 43,200
C ≥ 0
S ≥ 0
using solver, the optimal solution is 210C + 60S = $22,200,000