Answer:
$400,000
Step-by-step explanation:
Estimate at completion in finance can be explained as forecast cost of a particular project. It can be estimated by using the expression below
Estimate at completion =[Budget at Completion] /(Cost Performance Index)
From the question, our budget at completion for a project = $200,000
cost performance index is = 0 .5,
Then just input the values we have,
Estimate at completion= 200000/0.5
=$400,000
Therefore, Estimate at completion is
$400,000