Answer: See explanation
Step-by-step explanation:
a. The optimal order quantity can be calculated as:
= √2DS/H
where
D = 3 × 12 × 3487 × 0. 75
= 94149
Total cost incurred during purchase
= $1.55 + $0.70
= $2.25
Setup cost (S) = $186
Holding cost
= 32% × $2.25
= 0.32 × $2.25
= $0.72
Optimal order quantity
= √(2 × 94149 × 186)/0.72
= 6974.50
b. This will be calculated as:
Annual demand / EOQ
= 94149/6974.50
= 13.50
The company should order cotton 13.5 times per year.
c. Since the first order is needed on 1-July and lead time is 2 weeks, SYM should place the order before 17th June.
d. This will be:
= Annual demand / EOQ
= 94149/6974.50
= 13.5 orders
e. The resulting annual holding cost will be:
= 0.72 × (6974.50/2)
= 0.72 × 3487.25
= $2510.82
f. The resulting annual ordering will be:
= 94149/6974.50 × $186
= 13.5 × $186
= $2511