Answer:
Transfers-In
= Direct materials + Direct labor costs + Manufacturing overhead
= (90% * 100) + 46 + 76
= $212 million
Transfer-Out
= Cost transferred in * work completed
= 212 * 75%
= $159 million
Ending Balance
= Cost transferred in - Cost transferred out
= 212 - 159
= $53 million