Compute the discounted payback statistic for Project C if the appropriate cost of capital is 7 percent and the maximum allowable discounted payback period is three years. (Do not round intermediate calculations and round your final answer to 2 decimal places.)
Project C
Time: 0 1 2 3 4 5
Cash flow: –$1,400 $640 $600 $640 $380 $180
Should the project be accepted or rejected?
accepted