Answer:
Quarter Production
Q1 11000
Q2 62000
Q3 65000
Q4 0
This will generate lower production and inventory cost as it savesthe fixed cost of 30,000 if we produce in the fourth quarter.
Step-by-step explanation:
First, we construct the formula for the relevant cost:
Holding Cost: $0.50 per shovel
$0.50 x 2 x (Q2-48,000) + $0.50 x (Q1-11,000) = Holding Cost Q2
$0.50 x 1 x (Q3-64,000) = Holding Cost Q3
First, the restrictions:
P1 P2 P3 P4 are Integer
P1 < 65,000
P2 < 65,000
P3 < 65,000
P4 < 65,000
Then, we have the inventory formulas:
I1 = P1 - S1
I2 = P2 + I1 -S2
I3 = P3 + I2 - S3
I4 = P4 + I3 - S4
The holding cost
H1 = I1 x 0.50
H2 = I2 x 0.50
H3 = I3 x 0.50
H4 = I4 x 0.50
The fixed cost
if P1> 0 then FC1 = 30,000
if P2> 0 then FC2 = 30,000
if P3> 0 then FC3 = 30,000
if P4> 0 then FC4 = 30,000
And last,the total cost:
FC1 + H1 +FC2 + H2 +FC3 + H3 +FC4 + H4 = Total Cost
This is the formula we want to minimize
We place this into excel solver and get the answer: