Answer:
A) 114 tons
C) $22800
D) $22807.02
Step-by-step explanation:
Given Data:
annual holding cost (H) = 25% * $2000
setup cost (s) = $10000
production rate = 20
weekly demand = 5 tons
first we have to calculate the Annual demand , holding cost and the usage rate:
Annual demand = 5 tons * 52 weeks
= 260 tons
Holding cost (H) = 25% * $2000
= $500
Usage rate = (production rate) / (customer demand)
= 20 / 5 = 4 tons
A) Optimal production batch size of the mill
Qp =

=

= 114 tons
C) The annual inventory holding cost
Annual holding cost
=

Imax = ( Qp / P ) (p-u)
= (114 / 20 ) ( 20 - 4 )
= 91.2 tons
therefore Annual holding cost : = ( 91.2 / 2) * 500 = $22800
D) Annual setup cost of the plant
=

D = 260
Qp = 114
S = $10000
hence Annual setup cost of the plant
= (260/114) * 10000
= $22807.02