Answer:
B
Step-by-step explanation:
Green Cabinets is a custom cabinet builder. They recently completed a set of kitchen cabinets (Job Number 1478), as summarized below Job Number:1478 Date Started: 4/07/20x8 Date Completed: 4/22/20x8 Description: Cherry kitchen cabinets Applied Manufacturing Overhead Hours Direct Materials Direct Labor Req No Ticket 128 Amount Hours Amount Rate Amount $375 235 385 18 414 130 588 391 25 395 140 133 9 243 401 215 52 Total 965 Total $1,244 Cost Summary Direct Material Cost 965 Direct Labor Cost 1,244 Applied Manufacturing Overhead Total Cost Green Cabinets applies overhead to jobs at a rate of $12 per direct labor hour.