Answer:
$16.14
Step-by-step explanation:
Computation for the unit product cost that would appear on the job cost sheet
First step is to find the Total cost
Direct Material Cost 56,870
Direct Labor 6,305
Manufacturing Overhead Cost 6,226
Total Cost $69,401
Second step is to find the unit product cost
Using this formula
Unit product cost= Total Cost ÷ Number of units
Unit product cost= $69,401÷ 4,300
Unit product cost= $16.14
1) Calculation for Direct Labor Cost
Wage rate = $13 per labor hour
Direct Labor hours = 485
Direct Labor Cost = 485 * $13
Direct Labor Cost = $6,305
2) Calculation for Manufacturing Overhead Cost
Overhead rate = $11 per machine hour
Total machine hours = 566
Manufacturing Overhead Cost = $566*11
Manufacturing Overhead Cost =$6,226
Therefore the unit product cost that would appear on the job cost sheet will be $16.14