Answer:
Direct labor rate variance= $34,000 unfvorable
Direct labor time (efficiency) variance= $45,000 favorable
Step-by-step explanation:
Giving the following information:
Standard:
Expected activity of 24,000 units or 36,000 direct labor hours
Direct labor (1.5 hours at $90)
Actual:
Units produced 23,000
Direct labor hours worked 34,000
Direct labor costs $ 3,094,000
To calculate the direct labor rate and efficiency variance, we need to use the following formulas:
Direct labor rate variance= (Standard Rate - Actual Rate)*Actual Quantity
Actual rate= 3,094,000/34,000= $91 per hour
Direct labor rate variance= (90 - 91)*34,000
Direct labor rate variance= $34,000 unfvorable
Direct labor time (efficiency) variance= (Standard Quantity - Actual Quantity)*standard rate
Direct labor time (efficiency) variance= (23,000*1.5 - 34,000)*90
Direct labor time (efficiency) variance= $45,000 favorable