JFS Co. constructed a new subdivision during 2020 and 2021 under contract with National Hoopla Company. Relevant data are summarized below: Contract amount $ 3,000,000 Cost in the year: 2020 1,200,000 2021 600,000 Cost to complete: 2020 1,000,000 2021 800,000 Contract billings: 2020 1,500,000 2021 1,500,000 JFS recognizes revenue upon completion of the contract. In its December 31, 2020, balance sheet, JFS would report: Multiple Choice The contract asset, deferred profit, of $400,000. The contract asset, contract amount in excess of billings, of $1,500,000. The contract asset, cost and profits in excess of billings, of $500,000. The contract liability, billings in excess of cost, of $300,000.

1 Answer

5 votes

Answer:

The contract asset, cost and profits in excess of billings, of $500,000.

Step-by-step explanation:

As JFS follows completion contract method, the following will be recognized in the books for December 31, 2020:

1. Cost to Complete - $1,000,000

2. Revenue (billings done in 2020) $1,500,000

3. Profit - $500,000

Hence, the third option is correct

User Barry Fruitman
by
7.9k points

Related questions

asked Aug 8, 2021 134k views
Jeff Chen asked Aug 8, 2021
by Jeff Chen
7.6k points
2 answers
4 votes
134k views
asked Jul 9, 2021 232k views
One Lyner asked Jul 9, 2021
by One Lyner
8.0k points
1 answer
0 votes
232k views