Answer:
this company's reorder point should be 1,500 units of raw materials.
Step-by-step explanation:
The reorder point is the minimum level that you can hold on inventory before purchasing more materials. It is calculated by multiplying a company's daily needs (300 units per day) x the delivery lead time (5 days) = 1,500 units.
If the company decided to keep a safety stock, then in order to determine the minimum inventory level you would need to add the desired safety stock + 1,500 units.