Answer:
1½ miles/day .
Explanation:
To find:-
- The rate at which the construction crew built thr road.
Answer:-
It is given that the crew made 8¼ miles of road in 5½ days . To find the rate of work done , simply divide the total length of road nade by total time taken . That would be , ( rate is represented by "r" . )
Convert the mixed fraction into improper fraction.
For dividing them , multiply the reciprocal of 11/2 by 33/4 as ,
Hence the unit rate of constructing the road is 1½ miles/day .