Answer:
gross profit percentage of completion method:
2013: 726,300
2014: 841,700
2015: 432,000
completed contract
we recognize the profit at the end:
2013: zero
2014: zero
2015: 2,000,000
Step-by-step explanation:
percentage of completion
2013:
we incurred 2,300,000
over a total cost of 2,300,000 + 5,300,000 = 7,600,000
the percentage complete will be:
2,300,000 / 7,600,000 = 30.263% percentage of completion
we multiply this be the revenue:
$10,000,000 x 30,263% = $3,026,300
less 2,300,000 cost
gross profit: 726,300 dollars
2014:
we incurred 3,600,000
so far we have cost for 2,300,000 + 3,600,000 = 5,900,000
for a total cost of 7,900,000
5,900,000 / 7,900,000 = 74.68% percentage of completion
we multiply this but, subtract previous revenue recognized:
10,000,000 x (74.68% - 30,263%) = 4,441,700 revenue
less 3,600,000 cost: 841,700 gross profit
2015:
we complete the project so we recognize the rest of the revenue.
10,000,000 x (100% - 74.68%) = 2,532,000
cost of the year 2,100,000
gross profit: 432,000
completed contract:
10,000,000 contract value less cost:
2013 2,300,000
2014 3,600,000
2015 2,100,000
total 8,000,000
gross profit 2,000,000