Acklin Company has two products: A and B. Annual production and sales are 600 units of Product A and 900 units of Product B.The company has traditionally used direct labor-hours as the basis for applying all manufacturing overhead to products.Product A requires 0.5 direct labor hours per unit and Product B requires 0.3 direct labor hours per unit.The total estimated overhead cost for the next period is $63,322.The company is now considering switching to an activity-based costing system. The new activity-based costing system would have three overhead activity cost pools- Activity 1, Activity 2, and General Factory-with estimated overhead costs and expected activity as follows:Estimated Overhead Expected Activity (Allocation Base)Activity Pool Cost Product A Product B TotalActivity 1 $18,900 700 200 900Activity 2 15,631 1,000 100 1,100General factory 28,791 300 270 570Total $63,322 (Note: The General Factory activity pool's costs are allocated on the basis of direct labor hours.)1. The overhead cost per unit of Product A under the traditional costing system is closest to:A) $10.50B) $55.55C) $25.26D) $7.112. The overhead cost per unit of Product A under the activity-based costing system is closest to:A) $25.26B) $73.44C) $42.21D) $55.55

1 Answer

2 votes

Answer:

1. B $55.55

2.

Step-by-step explanation:

1. The overhead cost per unit of product A under the traditional costing system

Overhead cost per unit = Estimated manufacturing overhead / Direct labor hours

= $63,332 / (570 × 0.5)

= $55.55 per unit

2. Activity rate

User Scientiffic
by
7.8k points
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories