Answer:
All the numbers are missing, so I looked for a similar question.
The contract includes the production of 225,000 gear housings during 1 year.
We are also given the estimated costs of each alternative. We must choose the alternative that minimizes our total costs.
- total costs for general purpose equipment (GPE) = $125,000 + (225,000 x $15) = $3,500,000
- total costs for flexible manufacturing system (FMS) = $200,000 + (225,000 x $14.50) = $3,462,500
- total costs for dedicated machine (DM) = $525,000 + (225,000 x $13.50) = $3,562,500
For the current volume, the best option is flexible manufacturing system with a total cost of $3,462,500.
As total volume increases, the DM option becomes more attractive, but in order for it to cost less than FMS, total output should be higher than 325,000 units per year.
525,000 + 13.5x = 200,000 + 14.5x
x = 325,000 units
GPE is only attractive when the total units are lower (below 150,000 units per year):
125,000 + 15x = 200,000 + 14.5x
0.5x = 75,000
x = 150,000