Answer:
8 more men are needed to complete the job
Explanation:
Proportions
This problem can be solved by step-by-step reasoning applying proportions:
- 16 men working 9 hrs a day complete the job in 14 days
- 16 men working 1 hr a day complete the job in 14*9 days
The above statement stands because the fewer hours of work, the more time the job needs to be completed. Let's continue.
- 1 man working 1 hr a day complete the job in 14*9*16 days
The same reasoning applies here, fewer men=more days.
Now for the second condition. Increase the hours/day:
- 1 man working 7 hrs a day complete the job in 14*9*16/7 days
More hours/day=less days to complete the job
- x men working 7 hrs a day complete the job in 14*9*16/(7*x) days
We know this last time is 12 days, thus:
![\displaystyle 12=(14*9*16)/(7*x)](https://img.qammunity.org/2021/formulas/mathematics/high-school/l359llqy41pjqeroirtdntcaq3fqw8jc9m.png)
Solving for x:
![\displaystyle x=(14*9*16)/(7*12)=(2016)/(84)=24](https://img.qammunity.org/2021/formulas/mathematics/high-school/yerprhl3nq6v3bfufaru7byxg6yf191450.png)
24 men are needed now, this is an increase of 24-16=8 more men
8 more men are needed to complete the job