Answer:
(A) Navy contract= 1.0
Army contract= 0.8
(B) Navy contract
Step-by-step explanation:
(A) The productivity for navy can be calculated as follows
= 28 × 2× 40
= 2240
Since the navy contract was for 2266 devices then productivity is
= 2266/2240
= 1.0 labor hour
The productivity for army can be calculated as follows
= 29×6×40
= 6960
Since the army contract was for 5510 devices then productivity is
= 5510/6960
= 0.8 labor hour
(B) The workers were more productive on the navy contract