Answer:
$12,400
Explanation:
The computation of Job 82's total manufacturing cost in August using normal costing us shown below:-
Overhead rate = Budgeted Overhead ÷ Budgeted Labor cost
= $672,000 ÷ 1,680,000
= 40%
Applied overhead = 6000 × 40%
= 2,400
The Total cost of Job 82 = Direct material + Direct labor + Overhead applied
= $4,000 + $6,000 + $2,400
= $12,400