An incomplete cost of goods manufactured schedule is presented below. Complete the cost of goods manufactured schedule for Vaughn Company.

VAUGHN COMPANY
Cost of Goods Manufactured Schedule
Work in process (1/1) $220,940
Direct materials
Raw materials inventory (1/1) $
Add: Raw materials purchases 159,120
Total raw materials available for use
Less: Raw materials inventory (12/31) 22,610
Direct materials used $188,420
Direct labor
Manufacturing overhead
Indirect labor 25,620
Factory depreciation 37,200
Factory utilities 76,500
Total overhead 139,320
Total manufacturing costs
Total cost of work in process
Less: Work in process (12/31) 83,230
Cost of goods manufactured $544,240

User HiJump
by
5.7k points

1 Answer

6 votes

Answer:

Beginning Raw material Inventory = Direct materials used - Raw Materials purchases + Ending raw materials inventory

= 188,420 - 159,120 + 22,610

= $‭51,910‬

Total cost of work in process = Cost of goods manufactured + Work in process (12/31)

= 544,240 + 83,230

= $627,470

Total Manufacturing costs = Total cost of work in process - Work in process (1/1)

= 627,470 - 220,940

= $406,530

Direct labor = Total Manufacturing costs - Total overhead - Direct materials used

= 406,530 - 139,320 - 188,420

= $78,790