Answer:
(A) Current period productivity= 4 units/hr
Previous period productivity= 3.833units/hr
(B) increase in productivity by 4.356 percent
Step-by-step explanation:
A manager checkedthe rate of production and found out that a worker produced 160 units while working for 40 hours
In the previous week the same worker produced 138 units while working for 36 hours
(A) The current period productivity can be calculated as follows
= 160 units/40 hours
= 4 units/hr
The previous period productivity can be calculated as follows
= 138 units / 36 hours
= 3.833 units/hr
(B) The productivity growth can be calculated as follows
= current period productivity - previous period productivity / previous period productivity
= 4-3.833/3.833
= 0.167/3.833
= 0.04356 × 100
= 4.356 percent
Hence there was an increase in workers productivity by 4.356 percent