Answer:
The appropriated answer will be "$1,700,000".
Step-by-step explanation:
Revenue understood by completion percentage = Design balance throughout progress = $200,000
The percentage completion throughout the whole year will be:
⇒
![(200,000)/(2,000,000 )](https://img.qammunity.org/2021/formulas/business/college/z3ayzf824u94oh8e3wrsx1aixeukpm3k4l.png)
⇒
![10 \ percent](https://img.qammunity.org/2021/formulas/business/college/kacvbq74t26phu853zkqd0fedx6eq8jy5t.png)
The cost incurred throughout the whole year will be:
⇒
![Revenue \ recognized - Income \ on \ the \ contract](https://img.qammunity.org/2021/formulas/business/college/wwyctt8w91wng0zvdkrmm6fknwvw6zayyy.png)
⇒
![200,000 - 30,000](https://img.qammunity.org/2021/formulas/business/college/rwkod9zg6710xg2j3pbcsgciys3e3wx8w2.png)
⇒
($)
Now,
The total estimated cost of the project at the end the year 2021 will be:
⇒
![(170,000)/(10 \ percent)](https://img.qammunity.org/2021/formulas/business/college/11t33axte62oo5n33avuv7k4o89ecfk8q8.png)
⇒
($)