Answer:
$17,310,000
Step-by-step explanation:
Land purchased for use as warehouse and distribution site = $4.4 million(6 years ago)
Current market value of land = $4.7 million
For determining the initial investment in fixed assets for the plant, the current value of the land will have to be taken (as Parker and Stone would have had to buy land at this price for the plant, if the land was not already with it).
The amount spent on land will not be treated as sunk costs as this amount is not permanently lost. The company can recover money by selling the land. So the current market value will be included in the initial investment in fixed assets in reference to the project.
So, proper cash flow for the project = Site grading costs +Plant cost + Current market value of land
= $710,000 + $11.9 million + $4.7 million
= $17,310,000
Hence, $17,310,000 is the amount of initial investment in fixed assets to be used when evaluating this project.