Answer:
2040.
Step-by-step explanation:
To reach the total manufacturing cost we need to calculate machining and assembling overhead rate first, in order to calculate the rate we need to divide manufacturing overhead cost on number of hours
Machining OH rate = 280000 / 50000 = 5.60
Assembling OH rate = 360000/40000 = 9.00
manufacturing cost:
machine Assembly Total
Material 425 175 600
labor 275 300 575
Overhead 865
(50*5.60) 280
(65*9) 585