Answer:
Allocated MOH= $274,850
Step-by-step explanation:
Giving the following information:
Estimated manufacturing overhead cost $238,900
Estimated machine hours 20,000
Actual machine hours 23,000
First, we need to calculate the predetermined overhead rate:
Predetermined manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
Predetermined manufacturing overhead rate= 238,900/20,000
Predetermined manufacturing overhead rate= $11.945 per machine-hour
Now, we can allocate overhead:
Allocated MOH= Estimated manufacturing overhead rate* Actual amount of allocation base
Allocated MOH= 11.95*23,000
Allocated MOH= $274,850