Answer:
$40,500
Step-by-step explanation:
The computation of the total fixed cost is shown below:
= Factory building rent + Factory maintenance salaries + Factory supervisor’s salary, + depreciation expense + advertising cost
= $8,500 + $7,200 + $15,000 + $6,000 + $3,800
= $40,500
We simply applied the above formula So that the total fixed cost could come and the same is to be considered