Answer:
Allocated MOH= $825
Step-by-step explanation:
Giving the following information:
The company recently completed Job M800 which required 150 direct labor-hours.
First, we need to calculate the predetermined overhead rate:
Predetermined manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
Predetermined manufacturing overhead rate= (90,000/50,000) + 3.7
Predetermined manufacturing overhead rate= $5.5 per direct labor hour
Now, we can allocate overhead:
Allocated MOH= Estimated manufacturing overhead rate* Actual amount of allocation base
Allocated MOH= 5.5*150
Allocated MOH= $825