Answer:
B. $9,347
Step-by-step explanation:
Total direct labor = 37 direct labor hours * $24
Total direct labor = $888
Total overhead = $33 * 194 machine hours
Total overhead = $6,402
Total cost for the job = Direct materials + Direct labor + Overheads
Total cost for the job = 2057+888+6402
Total cost for the job = $9,347