Answer:
$34.73 per direct labor hour
Step-by-step explanation:
Predetermined overhead rate
= Estimated manufacturing overhead / Estimated labor hour
= [$1,245,216 + ( 43,600 × $6.17 ) ] / 43,600
= [$1,245,216 + $269,012] / 43,600
= $1,514,228 / 43,600
= $34.73 per direct labor hour
Therefore, the predetermined overhead rate for the recently completed year was closest to $34.73 per direct labor hour.