Answer:
1 $126
2 $140
3 90%
Step-by-step explanation:
1. Overhead applied = Closing balance of job - (opening balance of job + prime cost added to the job during the month
= $1,921 - ($1,235 + $560)
= $1,921 - $1,795
= $126
2. Direct labor for job 46 for July.
Direct labor = prime cost / ( 3 parts of direct materials + 1 part of direct labor)
Direct labor = $560 / 4
Direct labor = $140
Therefore, direct labor for job 46 for July is $140
Direct materials for job 46 for July
= Direct labor cost × 3(This is due to the fact that prime cost includes 3 parts of direct materials
= $140 × 3
= $420
3. Overhead rate for the company
= [($126 / $140) × 100
= 90%